Iron ore mining and processing plant, Russia
Tasks:
Technical solution:
Selection and delivery of equipment, technical support for installation work and supervision of commissioning works.
Uniqueness of the project:
The average service life of such machines is 20-25 years. It was necessary to implement the project and deliver equipment that would allow the customer to effectively use it in their process projects in the long term, while reducing operating costs for repairs.
Result:
The equipment was installed and put into operation within the agreed time frame.
Tasks:
- Delivery of new equipment as part of the construction of Crushing and Conveyor Complex
- Providing the Customer with reliable equipment in the shortest possible time, meeting all the declared parameters of productivity and reliability, while reducing the cost of the machine with a comparable level of quality and reliability.
Technical solution:
Selection and delivery of equipment, technical support for installation work and supervision of commissioning works.
Uniqueness of the project:
The average service life of such machines is 20-25 years. It was necessary to implement the project and deliver equipment that would allow the customer to effectively use it in their process projects in the long term, while reducing operating costs for repairs.
Result:
The equipment was installed and put into operation within the agreed time frame.